What the customer receives

BuildVerify example report

The paid deliverable is a structured document the customer keeps, not a chat transcript.

A complete sample document, written the way BuildVerify writes one. The customer, the numbers and the sources are illustrative.

BuildVerify Quote audit

Quote Audit · USD 49

A competent quote with four exclusions that will become variations

One contractor quote read line by line for what it covers, what it excludes and what it leaves undecided.

Prepared for
Marta and Ciaran B. · loft conversion, Dublin
Reference
BV-4429-QA
Issued
7 October 2026
Settlement
$VERIFY · USDC on Base

This is a better quote than most. It is itemised, the contractor has clearly visited, and the stage payments are reasonable. It also contains four exclusions and three undecided items that, on a job of this type, reliably turn into extra cost later. None of that makes it a bad quote. It makes it an incomplete price.

Competent, and not the final number

The quoted USD 68,400 is realistic for the work described. Four excluded items are near certain to be needed and are not priced, and on comparable jobs they add USD 6,000 to USD 11,000. Get them priced now, while you still have competitive leverage.

USD 68,400 Quoted
4 Exclusions likely to be needed
USD 6k to 11k Likely additional
3 Undecided items
01

What is good

The parts that do not need attention

Worth stating, because most of this quote is fine and you should not go into the conversation as though it is not.

  • Itemised by trade rather than one lump sum
  • Structural steel specified with sizes, not just allowed for
  • Stage payments tied to completed stages, not to dates
  • Waste removal and skips included and named
  • Making good after first fix is explicitly included
  • Contractor has visited and references the actual joist spacing
  • Start and duration stated, with a weather allowance
  • Insurance details and registration number on the document
02

Exclusions

What is not in the price

Excluded itemWill you need it?Typical costSeverity
Structural engineer calculations and drawings Yes. Required for the steel and for sign-off USD 900 to 1,600 Certain
Fire door upgrades to the existing landing Yes. Standard requirement for a loft conversion at this height USD 1,400 to 2,600 Certain
Electrical certification Yes. Needed for completion and for any future sale USD 350 to 600 Certain
Flooring finish Yes, unless you are leaving boards USD 1,800 to 3,400 Likely
Decorating Quote says bare plaster finish USD 1,500 to 2,800 Likely
Relocating the water tank Depends. The quote assumes it stays USD 800 to 1,900 Possible
Range if all four certain items apply USD 6,050 to 11,000

Exclusions are not dishonest. Every contractor excludes things, and a quote that excluded nothing would be a quote with padding in it. The risk is comparing this against another quote that includes some of these, which is how two honest quotes end up looking thousands apart.

03

Ambiguity

Wording that will be argued about

Phrase in the quoteWhat it could meanAsk
Allowance of USD 2,400 for staircase A budget, not a price. Yours to overspend What staircase does USD 2,400 actually buy, with a product reference?
Velux windows, two, standard Size, glazing and blind provision all unstated Which model, what size, and is a blind included?
Insulation to current standards Which standard, and who confirms it What U-value, and will you certify it?
Subject to access Undefined. Could cover almost anything later What access are you assuming, and what would change the price?
Plastering to a paint-ready finish Reasonable, but paint-ready is subjective Skim finish throughout, or patch and fill?
Client to supply sanitaryware Clear, but no deadline given By what date do you need it on site?

The allowance line is the most common source of dispute in a loft conversion quote. An allowance transfers the price risk to you, and until you know what it buys you do not know what the job costs.

04

Action

What to send back

One email, all questions together. Contractors answer a single consolidated list far better than six separate messages, and asking now costs nothing while asking later costs a variation.

  1. Before anything

    Ask for the four certain exclusions to be priced

    Engineer, fire doors, electrical certification, flooring. You are not committing to buy them from this contractor. You are finding out the real number.

  2. Same email

    Ask the six ambiguity questions in section 03

    Verbatim. The answers become part of the contract whether or not anyone intends that.

  3. Same email

    Ask what is excluded that is not listed

    An open question. Good contractors answer it honestly and the answer tells you a lot about who you are dealing with.

  4. Before signing

    Confirm who deals with building control

    The quote does not say. On a loft conversion this matters and it is a real amount of work for somebody.

  5. Before signing

    Get the revised total in writing

    Original plus priced exclusions, as one document with a date. That is the number to compare against other quotes and to hold the contractor to.

BuildVerify document audit · not a survey · confidential to the buyer · 7 October 2026 BuildVerify · $VERIFY
The order behind this document
Format

Structured document with tables, checklists and cited evidence.

Back to BuildVerify →