What the customer receives

BidEngineer example proposal outline

This Organization does not design anything and does not sign anything. It maps the client's specification to your capability line by line, so that every technical promise in the proposal traces back to a requirement and to evidence.

A complete sample document, written the way BidEngineer writes one. The customer, the numbers and the sources are illustrative.

BidEngineer Technical proposal outline

Technical Proposal Outline · USD 49

Wastewater pumping station upgrade: 34 requirements, 9 you cannot yet meet

Every clause of the technical specification mapped to a response, an owner and the evidence behind it. Four of the nine are mandatory.

Prepared for
Calder Process Engineering · bid team of four
Reference
BE-O-50912
Issued
1 October 2026
Settlement
$SPEC · USDC on Base

The specification has 34 numbered technical requirements. You can fully comply with 25. Of the nine you cannot, four are marked mandatory by the client, and three of those four are solvable this week with a subcontractor letter or a clarification question. The fourth is not, and it needs a decision from your directors.

Bid it, but resolve M-12 before committing the bid team

Requirement M-12 asks for ATEX zone 1 certified installation experience on three comparable schemes in the last five years. Calder has two. Partnering covers it; claiming three does not, and this is a client who checks. That is a director level decision and everything else in the bid depends on it.

34 Technical requirements
25 Full compliance
9 Partial or none
4 Of those, mandatory
1

Position

Compliance at a glance

Requirements by compliance status · requirements
Full compliance, evidenced 25
Partial, needs a partner 5
Partial, needs clarification 3
No compliance 1
SectionReqsFullGaps
1. Mechanical, pumps and pipework 9 9 None
2. Electrical and control 8 5 M-12, E-04, E-07
3. Civil and structural 5 4 C-03
4. Commissioning and testing 4 3 T-02
5. Health, safety and environment 5 4 H-05
6. Programme and resourcing 3 0 All three, see clause 4

Section 6 shows zero not because you cannot comply but because programme and resourcing cannot be answered until the M-12 partnering decision is made. They are blocked, not failed.

2

Matrix

The nine gaps, in the client's own numbering

RefRequirementStatusRoute to compliance
M-12 ATEX zone 1 installation, 3 comparable schemes in 5 years Partial. We have 2 Partner, or do not bid
E-04 SCADA integration with client's existing Telemetry platform None Subcontract. Two firms identified
E-07 Functional safety assessment to SIL 2 Partial Requires a qualified assessor
H-05 Confined space rescue capability on site Partial Specialist standby provider
C-03 Piling within 3 m of a live main Partial Done before, evidence is thin
T-02 Witnessed 72 hour performance test Partial Clarification: witnessed by whom?
P-01 Named site manager at tender Blocked Depends on M-12
P-02 Resource loaded programme Blocked Depends on M-12
P-03 Commitment to a 26 week programme Blocked Depends on M-12 and on C-03

Mandatory requirements are shown in bold. The client's instructions say a non compliance against any mandatory requirement may render the tender non compliant, which is the wording that makes M-12 a decision rather than a drafting problem.

3

Scope

Scope and exclusions, drafted

Drafted from the specification and from what you have said you will and will not do. Every exclusion below is here because leaving it unstated would mean you had priced something you did not intend to.

In scopeExcluded
Pump supply and installation, 3 duty 1 standby Yes
Pipework, valves and penetrations Yes
Wet well modification Yes
Electrical installation and MCC Yes
SCADA integration Subcontracted, named
Site survey and ground investigation By client, per spec 1.4
Diversion of the incoming main By others
Temporary overpumping during works Excluded, see assumption 4
Decommissioning of the existing plant Yes
Disposal of contaminated arisings Provisional sum
4

Assumptions

What the proposal assumes

#AssumptionIf wrong
1 Site available 07:00 to 18:00, six days Programme extends. 26 weeks becomes 32
2 Existing wet well structure is sound Structural works, unpriced
3 Ground investigation data supplied by client is accurate C-03 piling approach changes
4 Client provides temporary overpumping Significant cost, unpriced
5 Power supply capacity is adequate Supply upgrade, long lead
6 No asbestos in the existing building Survey and removal
7 Client witness available within 5 days for T-02 Commissioning float consumed
8 Permits issued within 10 working days Start on site slips

Eight assumptions is not excessive for a scheme of this type. What matters is that every one of them appears in the submitted proposal in these words. An assumption held in the estimator's head is not an assumption, it is a risk you have accepted silently.

5

Clarify

Five questions, and the deadline to ask them

Clarification deadline is 17 October, submission 7 November. All five are answerable by the client and all five change either the price or the compliance position.

  1. Who provides temporary overpumping during the works? Assumption 4 and the largest single unpriced item.
  2. M-12 asks for three comparable ATEX zone 1 schemes. Does experience held by a named subcontractor or partner count towards this requirement?
  3. T-02: who witnesses the 72 hour performance test, and what notice is required?
  4. Is the ground investigation report at appendix C the full set, or is there additional borehole data?
  5. E-07 requires a SIL 2 functional safety assessment. Is the assessor appointed by the client or by the contractor?
  • Ask all five by 17 October. After that the ambiguity is yours
  • Do not state compliance with M-12 until question 2 is answered in writing
  • Every assumption in clause 4 goes into the submitted document, verbatim
  • Every technical claim traces to a named project or a certificate before submission
  • Directors decide on M-12 before the bid team spends another week
BE-O-50912 · clarifications close 17 October · submission 7 November · $SPEC · 1 October 2026 BidEngineer · $SPEC
The order behind this document
Format

A compliance matrix against the client's own clause numbering, the scope and exclusions drafted, and the clarifications that must be raised before the deadline.