BuildPath example report

The paid deliverable is a structured document the customer keeps, not a chat transcript.

A complete sample document, written the way BuildPath writes one. The customer, the numbers and the sources are illustrative.

BuildPath Room renovation plan

Room Renovation Plan · USD 29

Kitchen, 1930s semi, Sheffield

The order of work, which trade comes when, what you decide before anyone starts, and the four things that make a kitchen overrun.

Prepared for
Owen and Ruth T. · first renovation, living in the house
Reference
BP-3325-RRP
Issued
27 September 2026
Settlement
$BLD · USDC on Base

You know what you want the kitchen to look like. This plan is about the order it has to happen in, because sequencing is where first renovations lose money. Every item below exists to stop one of two things: a trade arriving before the work they need is done, or a decision being made after the point where changing it costs real money.

Five weeks, if three decisions land early

A kitchen of this size is a five week job with the trades sequenced correctly and seven weeks with them sequenced the way most homeowners do it. Three decisions, appliances, tiles and the sink, must be final before the plasterer books, and all three are currently open.

5 wks With correct sequencing
6 Trades, in a fixed order
3 Decisions blocking the start
12% Contingency recommended
01

Order

Who comes when, and why

Trade windows across the five weeks. The overlaps are deliberate and the gaps are drying time, which cannot be compressed by paying anyone more.

Trade sequence, by week
Strip out and skip Days 1 to 3
Structural, if opening up Days 3 to 6 Only if the wall goes. Building control first
First fix plumbing Week 2, early
First fix electrics Week 2 After plumbing. Pipes before cables
Plastering Week 2 to 3 Decisions must be final
Drying out 5 to 8 days Nobody can speed this up
Flooring Week 4, early
Kitchen fitting Week 4 to 5
Worktop template and fit Week 5 Template only after units are in. Then 7 to 10 days
Second fix and tiling Week 5
Decorating and snagging Week 5, end
StartWk 1Wk 2Wk 3Wk 4Wk 5

Two items are commonly got wrong. Electrics before plumbing means a cable in the way of a waste pipe, and worktop templating before the units are fitted means a worktop that does not fit. Both add a week.

02

Decisions

What has to be final, and when

DecisionFinal byWhat it blocksCost of changing later
Appliance list and sizes Before first fix Plumbing and electrical positions High. Chasing walls again
Sink position and type Before first fix Waste run, and whether the island is possible High
Tile choice Before plastering Wall build-up and therefore unit depth Medium
Layout and unit run Before ordering Everything Very high
Worktop material Before templating Lead time only Low, if before week 4
Handles and paint Before second fix Nothing Low
Lighting positions Before first fix electrics Ceiling work and plastering Medium

Handles and paint are the decisions people agonise over and they are the two that can be left latest. Appliances and the sink are the ones people leave open and they are the two that cost the most to change.

03

Budget

Where the money goes, and what is usually forgotten

Budget categories for a kitchen of this size
Units and worktop 34%
Labour, all trades 26%
Appliances 14%
Flooring 7%
Electrics and plumbing materials 6%
Tiling and decorating 5%
Skip, waste and access 3% Always forgotten
Eating out while no kitchen 5% Never in anyone's budget

Percentages of total project cost, from typical UK kitchen projects at this scale. The last two rows are the ones missing from almost every homeowner spreadsheet, and together they are eight percent.

04

Quotes

Making contractors quote the same thing

Quotes are only comparable if they cover the same scope. These are the eight lines that are usually missing, and the reason two quotes can differ by 30 percent and both be honest.

  • Who supplies the units, you or them
  • Is making good and plastering included after first fix
  • Skip hire and waste removal, in or out
  • Is the electrical certificate included
  • Who templates and fits the worktop
  • Is decorating included or is it a bare plastered finish
  • What happens if the floor needs levelling
  • Payment stages, and what is due before anyone starts
StageTypical paymentDo not
Booking Nothing, or a small deposit Pay more than 10 percent before work starts
Materials On delivery to site, evidenced Pay for materials you cannot see
First fix complete Stage payment Pay ahead of completed stages
Units fitted Stage payment
Snagging complete Final balance, after your list is cleared Pay the final balance before snagging

Holding a meaningful final payment until your snagging list is cleared is the only leverage you have at the end of a job, and it is the thing first-time renovators give away.

05

Living in it

Five weeks without a kitchen

  1. Before week 1

    Set up a temporary kitchen somewhere else

    Kettle, microwave, air fryer, a table, the fridge relocated. Do this before the strip out, not during it.

  2. Week 1

    Agree working hours and a dust plan in writing

    Start time, finish time, which door they use, where the skip goes, and dust sheeting on the route through the house.

  3. Weekly

    One fifteen minute walk round with the lead trade

    Same day each week. Most disputes on small projects come from decisions made on site that nobody told the owner about.

  4. Week 3

    Do not add anything

    The mid-project extra is the most expensive money in any renovation. Write it down and do it after, as its own job.

  5. Week 5

    Snag in daylight, with a list

    Room empty, lights off, natural light. Photograph everything, one list, one email. Then release the final payment.

BuildPath renovation plan · confidential to the buyer · 27 September 2026 BuildPath · $BLD
The order behind this document
Format